Erkwood/Shepherd roundabout update

At yesterday’s Henderson County Transportation Advisory Committee (TAC) meeting, NCDOT gave an update on the Erkwood Drive/Shepherd Street roundabout that is affecting Greenville Highway:

  • Current date to end the detour and reopen Greenville Highway: October 22 (this is a few days later than the original October 17 date)
  • Project now considered 43% complete

The photo above was taken from Greenville Highway south looking north. Below is a photo from Shepherd Street looking west (and yes, the white house is still standing).

Roundabout_Shepherd_20190919

One thought on “Erkwood/Shepherd roundabout update

Add yours

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑

%d bloggers like this: